Metodología del seguimiento efectivo al plazo contractual de proyectos de construcción de edificaciones multifamiliares
Average rating
Cast your vote
You can rate an item by clicking the amount of stars they wish to award to this item.
When enough users have cast their vote on this item, the average rating will also be shown.
Star rating
Your vote was cast
Thank you for your feedback
Thank you for your feedback
Advisors
Palacios Lizier, Carlos AndrésIssue Date
2019-08-23Keywords
PMIPRINCE2
Lean construction
Último Planificador
Implementación Lean
Seguimiento y Control de Cronograma
Retrasos en la Construcción
Lean construction
Last Planner
Lean Implementation
Schedule Tracking and Control
Construction Delay
Metadata
Show full item recordAbstract
La presente investigación abunda en los conceptos relacionados a los retrasos que ocurren en una obra y a las causas del ineficiente seguimiento y control realizado al cronograma contractual de proyectos de construcción de la ciudad de Lima Metropolitana. Asimismo, se recaudó información de metodologías y herramientas a la vanguardia y se levantó la información de 3 proyectos de construcción de edificaciones multifamiliares. A partir de la información de estos proyectos, se identificaron los principales problemas de cada metodología que terminaron causando retrasos sobre los plazos contractuales de los mismos. Estos problemas pudieron ser agrupados en tres principalmente: la inadecuada planificación, la inadecuada programación y el vínculo débil o inexistente entre ambos. A partir de lo mencionado, se propuso una metodología con el principal objetivo de brindar una guía hacia los contratistas para realizar un seguimiento efectivo al plazo contractual de sus proyectos y prevenir todo retraso.This investigation reviews the concepts related to the delays that occur in construction projects and the causes of the inefficient monitoring and control made to the contractual schedule in multi-family building projects developed in the city of Lima, Peru. Information was collected on methodologies and tools being used worldwide as well as from 3 multi-family constriction building projects. From the information of these projects, the main problems of each methodology that ended up causing delays over their contractual schedule were identified. Problems identified were grouped into three: inadequate planning, inadequate programming and a weak or non-existent link between the two. Based on this analysis, a methodology was proposed with the main purpose of providing a guide to contractors to effectively monitor the contractual schedule of their projects and prevent any delay.
Type
info:eu-repo/semantics/bachelorThesisRights
info:eu-repo/semantics/openAccessAttribution-NonCommercial-ShareAlike 4.0 International
Language
spaCollections
The following license files are associated with this item:
- Creative Commons